  • Project Date: 1.5.2017
  • Existing Project

(Small scale) ssLNG to Power

KSE LED JOINT VENTURE


POWER PROJECT DEVELOPMENT

ssLNG based 'Virtual gas pipeline'

 

CATEGORY

Existing Project

 

PROJECT DETAILS

• Well head and LNG liquefaction in Tanzania

• Transported into Zambia and Botswana

• Road transport of LNG, 2243km between Kilwa Masoko depot, TZ and Ndola

• LNG Fuelling solution for various mines, tourism and other industry reduces fuel cost by +50%

• LNG based 250kW-10MW small-scale power generation solutions, rural off-grid electrification

• Hybrid Solar+LNG (balancing fuel) for 5-6 hr/day solarpeak hours

• Delivered LNG fuel price of $8.50 - $10.50/GJ HHV depending on volumes & distance

 

PHASE I

• 10 MMscfd of produced gas (12 hrs/day, 7 days/wk @110MW) at the well-head under term-sheet with KSE, more available as required

PHASE II

• Up to 40 MMscfd being considered for growth of consumers from mining, tourism, transportation, etc.